Deadlines for Energy Credit Facility Construction

Continuity Safe Harbor Deadlines for Energy Credit Facility Construction May be Delayed for National Security Concerns

The continuity safe harbor placed-in-service date deadlines for the investment tax energy credit (Internal Revenue Code (IRC) Section 48) and the renewable electricity production credit (IRC Section 45(a)) may be tolled if a construction delay is caused by national security concerns raised by the Department of Defense (DOD).

Background

In general, the energy credit may only be claimed if construction on a qualified facility begins before January 1, 2022. In the case of the production credit, construction must have started before January 1, 2017 (January 1, 2020 for a wind facility). Once construction begins, taxpayers are required to make continuous progress toward completion under either a continuous construction test or a continuous efforts test. These tests are deemed satisfied under the continuity safe harbor if the facility is placed in service within four
calendar years after the calendar year in which construction begins.

Tolling Requirements

A construction deadline in the continuity safe harbor is tolled if all of the following requirements are satisfied:

  • one or more necessary government permits or approvals for construction have been issued;
  • construction has begun;
  • the DOD provides written notice that the construction plan should be modified in the interest of national security;
  • the plan is modified in a way that is acceptable to the DOD to mitigate the national security concerns; and
  • as a result of the plan modification, new or additional permits or licenses must be obtained which will delay the placed-in-service date of the facility or energy property.

Tolling Period

The tolling period of the continuity safe harbor begins on the day the DOD provides written notice that the plan of construction requires modification to meet national security concerns. The tolling period ends when one of the following events occurs:

  • all new or additional permits or licenses are obtained;
  • written confirmation is received that all of the required new or additional permits or licenses will not be issued; or
  • the relevant federal or state authorities are notified in writing that the modification to the plan will no longer be pursued.

The maximum length of the tolling period is four years.

No Rulings

The IRS will not issue private letter rulings or determination letters regarding the application of the tolling provision or the beginning of construction requirement.

For more information about this article, please contact our tax professionals at taxalerts@windes.com or toll free at 844.4WINDES (844.494.6337).